Power String Failure Analysis โ UPS, Generator & Transformer Sizing
๐๏ธ Topology
Combined: IT and mechanical loads share the same power strings. This is the existing sizing methodology.
๐ System Parameters
STEP 1 Rack Row IT Loads
Define the kW load for each rack row. Default is uniform distribution.
Row
Load (kW)
Racks
Feed Type
STEP 2 Busbar Distribution & String Allocation
Dual: Each row fed by 2 busbars (50/50 split). On failure, surviving busbar takes 100%.
๐ง Other Loads Per String (Non-IT, fixed)
Mechanical and other fixed loads per string. Do NOT redistribute on failure.
String
Chiller Electrical Load (kW)
Misc (kW)
Total
๐ Fan Wall Units
Fan wall units are structured mech UPS loads. In normal operation, the full unit load sits on the primary string. On primary string failure, the full load transfers to the secondary string.
Unit
Load (kW)
Primary String
Secondary String
๐ Mech UPS Loads Per String
Other dedicated mechanical UPS output loads per string, separate from fan wall units.
String
Other Mech UPS Load (kW)
โ๏ธ Mechanical Topology (Separated)
Mechanical strings are independent from IT strings. Labels prefixed with M-. Power factors and distribution loss are shared with the IT calculation.
Each Mech string carries one dedicated chiller load + one dedicated Mech UPS load. Fan wall count is shared with the IT topology above.
โ๏ธ Mech Other Loads Per String
Per-string chiller / misc loads. The ATS Backup String transfers both the chiller and the Mech UPS load of this string to the nominated backup on failure. Misc loads drop out.
Mech String
Chiller Electrical Load (kW)
Misc (kW)
ATS Backup String
Total
โ๏ธ Mech Fan Wall Units
Fan wall units across the Mech strings. Primary string failure transfers the unit load to its secondary.
Unit
Load (kW)
Primary Mech String
Secondary Mech String
โ๏ธ Mech UPS Loads Per String
Dedicated Mech UPS output loads per Mech string. On Mech string failure these transfer using the same ATS backup as the chiller above.
Mech String
Other Mech UPS Load (kW)
ATS Backup (from Other Loads)
๐งพ Executive Summary
๐ Assumptions & Methodology
Show calculation assumptions
UPS sizing can be configured as either IT-only UPS with separate mechanical UPS reporting, or combined IT + mech UPS where the entered Mech UPS load is included in the main UPS sizing basis.
Mechanical / cooling / miscellaneous loads do not redistribute during failure scenarios.
UPS input power is calculated from UPS output plus configured charging and UPS losses.
Generator sizing is based on worst-case surviving string demand with distribution losses first applied to UPS output, then UPS charging and losses applied to that adjusted UPS demand, then fixed non-IT loads added, then a further distribution loss allowance applied to the combined total before conversion by entered power factor.
In separate UPS mode, the tool also reports mechanical UPS output and input from the entered Mech UPS loads and Fan Wall units for visibility, while generator sizing still uses the combined load basis.
Transformer sizing is selected from the entered transformer rating list using the calculated generator apparent power.
Dual mode assumes all racks are dual-connected across A/B, with each string carrying 50% of every rack load in normal operation and the survivor taking 100% on failure.
Triple mode assumes the first rack half is dual-connected across A/C and the second half across B/C, with each connected pair sharing 50/50 in normal operation.
Quad mode assumes two independent paired paths (A/B and C/D), each redistributing only within its pair.
Quint mode assumes rack groups are dual-connected across A/E, B/E, C/E and D/E, with each connected pair sharing 50/50 in normal operation.
Hex mode uses 6 strings with dual catchers (E and F) and always applies Quad (4S) feed. Left half of racks are quad-connected across A/B/E/F; right half across C/D/E/F. Each connected string carries 25% in normal. On failure of any one string, the surviving 3 feeds in that half take 33.3% each.
Rack Feed Types:Dual โ 2 feeds from assigned strings (default). Quad (2S) โ 4 feeds from the same 2 assigned strings (physical redundancy, no calculation change). Quad (4S) โ 4 feeds from 4 separate strings; in Quad mode this changes the calculation to 25% per string in normal, with the remaining 3 strings each taking 33.3% on failure. In other modes Quad (4S) behaves like Quad (2S) as racks connect to โค2 distinct strings.
Validation warnings are advisory checks only and currently use these thresholds:
Normal IT load imbalance: moderate warning above 5%; high warning above 10%.
Governing failure uplift: material warning above 20% over normal IT load on the affected surviving string; severe warning above 40%.
Generator / UPS / Transformer power factors: warning when any entered PF is below 0.80 or above 1.00.
UPS charging allowance: warning when above 8%.
UPS loss allowance: warning when above 8%.
Distribution loss allowance: advisory warning when above 5%.
Transformer ratings: warning when no valid transformer ratings can be parsed from the input list.
Duplicate feed selections: warning when the same string is assigned more than once within a single row definition.
๐ Row-Level Normal Distribution
IT load contribution from each row to each string under normal operation (rack-based physical split).
๐ Normal Operation Summary
String
IT Load (kW)
Other Load (kW)
IT UPS Output (kW)
IT UPS Input (kW)
Mech UPS Output (kW)
Mech UPS Input (kW)
Gen Load (kW)
Gen (kVA)
โก Failure Scenario Matrix โ UPS Output (kW)
UPS output on each surviving string per failure. "โ" = failed string.
๐ง Equipment Sizing
String
Worst UPS Out (kW)
UPS Input (kW)
UPS (kVA)
Gen (kW)
Gen (kVA)
Transformer Calc (kVA)
Transformer Std (kVA)
Scenario
๐ Mech UPS Failure Scenario Matrix
Mech UPS output on each surviving string per failure. Includes Fan Wall transfer plus other mech UPS loads.
๐ Mech UPS Failure Sizing
String
Worst Mech UPS Output (kW)
Worst Mech UPS Input (kW)
Mech UPS (kVA)
Scenario
โ๏ธ Separated Mechanical Topology โ Results
Independent mechanical string bank. Chiller and Mech UPS loads transfer to the nominated ATS backup string on failure. Misc loads drop out.
โ๏ธ Mech Normal Operation Summary
Mech String
Chiller (kW)
Misc (kW)
Fan Wall (kW)
Mech UPS Load (kW)
Mech UPS Output (kW)
Mech UPS Input (kW)
Mech UPS (kVA)
Gen Load (kW)
Gen (kVA)
โ๏ธ Mech UPS Failure Scenario Matrix
Mech UPS output on each surviving string per failure (fan wall transfer + chiller/Mech UPS ATS transfer).
โ๏ธ Mech Generator Failure Scenario Matrix
Total generator load on each surviving string per failure (UPS input + chiller + misc).
โ๏ธ Mech Equipment Sizing
Mech String
Worst UPS Out (kW)
UPS Input (kW)
UPS (kVA)
Gen (kW)
Gen (kVA)
Transformer Calc (kVA)
Transformer Std (kVA)
UPS Scenario
Gen Scenario
๐ Multi-Scenario Comparison
Current configuration is Scenario 0 (baseline). Export a template for additional scenarios, fill in different row loads, then import to compare all results side by side.
๐ Scenario Comparison Summary
Separated topology detected โ mechanical loads are excluded from this comparison. IT UPS / Generator / Transformer sizing only.