Data centre server hall

โšก DC Failure Scenario & Equipment Sizing Tool

Power String Failure Analysis โ€” UPS, Generator & Transformer Sizing

๐Ÿ—๏ธ Topology

Combined: IT and mechanical loads share the same power strings. This is the existing sizing methodology.

๐Ÿ“Š System Parameters

STEP 1 Rack Row IT Loads

Define the kW load for each rack row. Default is uniform distribution.

RowLoad (kW)RacksFeed Type

STEP 2 Busbar Distribution & String Allocation

Dual: Each row fed by 2 busbars (50/50 split). On failure, surviving busbar takes 100%.

๐Ÿ”ง Other Loads Per String (Non-IT, fixed)

Mechanical and other fixed loads per string. Do NOT redistribute on failure.

StringChiller Electrical Load (kW)Misc (kW)Total

๐ŸŒ€ Fan Wall Units

Fan wall units are structured mech UPS loads. In normal operation, the full unit load sits on the primary string. On primary string failure, the full load transfers to the secondary string.

UnitLoad (kW)Primary StringSecondary String

๐Ÿ”‹ Mech UPS Loads Per String

Other dedicated mechanical UPS output loads per string, separate from fan wall units.

StringOther Mech UPS Load (kW)

๐Ÿงพ Executive Summary

๐Ÿ“˜ Assumptions & Methodology

Show calculation assumptions
  • UPS sizing can be configured as either IT-only UPS with separate mechanical UPS reporting, or combined IT + mech UPS where the entered Mech UPS load is included in the main UPS sizing basis.
  • Mechanical / cooling / miscellaneous loads do not redistribute during failure scenarios.
  • UPS input power is calculated from UPS output plus configured charging and UPS losses.
  • Generator sizing is based on worst-case surviving string demand with distribution losses first applied to UPS output, then UPS charging and losses applied to that adjusted UPS demand, then fixed non-IT loads added, then a further distribution loss allowance applied to the combined total before conversion by entered power factor.
  • In separate UPS mode, the tool also reports mechanical UPS output and input from the entered Mech UPS loads and Fan Wall units for visibility, while generator sizing still uses the combined load basis.
  • Transformer sizing is selected from the entered transformer rating list using the calculated generator apparent power.
  • Dual mode assumes all racks are dual-connected across A/B, with each string carrying 50% of every rack load in normal operation and the survivor taking 100% on failure.
  • Triple mode assumes the first rack half is dual-connected across A/C and the second half across B/C, with each connected pair sharing 50/50 in normal operation.
  • Quad mode assumes two independent paired paths (A/B and C/D), each redistributing only within its pair.
  • Quint mode assumes rack groups are dual-connected across A/E, B/E, C/E and D/E, with each connected pair sharing 50/50 in normal operation.
  • Hex mode uses 6 strings with dual catchers (E and F) and always applies Quad (4S) feed. Left half of racks are quad-connected across A/B/E/F; right half across C/D/E/F. Each connected string carries 25% in normal. On failure of any one string, the surviving 3 feeds in that half take 33.3% each.
  • Rack Feed Types: Dual โ€” 2 feeds from assigned strings (default). Quad (2S) โ€” 4 feeds from the same 2 assigned strings (physical redundancy, no calculation change). Quad (4S) โ€” 4 feeds from 4 separate strings; in Quad mode this changes the calculation to 25% per string in normal, with the remaining 3 strings each taking 33.3% on failure. In other modes Quad (4S) behaves like Quad (2S) as racks connect to โ‰ค2 distinct strings.
  • Validation warnings are advisory checks only and currently use these thresholds:
  • Normal IT load imbalance: moderate warning above 5%; high warning above 10%.
  • Governing failure uplift: material warning above 20% over normal IT load on the affected surviving string; severe warning above 40%.
  • Generator / UPS / Transformer power factors: warning when any entered PF is below 0.80 or above 1.00.
  • UPS charging allowance: warning when above 8%.
  • UPS loss allowance: warning when above 8%.
  • Distribution loss allowance: advisory warning when above 5%.
  • Transformer ratings: warning when no valid transformer ratings can be parsed from the input list.
  • Duplicate feed selections: warning when the same string is assigned more than once within a single row definition.

๐Ÿ“Š Row-Level Normal Distribution

IT load contribution from each row to each string under normal operation (rack-based physical split).

๐Ÿ“Š Normal Operation Summary

StringIT Load (kW)Other Load (kW)IT UPS Output (kW)IT UPS Input (kW)Mech UPS Output (kW)Mech UPS Input (kW)Gen Load (kW)Gen (kVA)

โšก Failure Scenario Matrix โ€” UPS Output (kW)

UPS output on each surviving string per failure. "โ€”" = failed string.

๐Ÿ”ง Equipment Sizing

StringWorst UPS Out (kW)UPS Input (kW)UPS (kVA)Gen (kW)Gen (kVA)Transformer Calc (kVA)Transformer Std (kVA)Scenario

๐Ÿ”„ Multi-Scenario Comparison

Current configuration is Scenario 0 (baseline). Export a template for additional scenarios, fill in different row loads, then import to compare all results side by side.